IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
Arb. Case No.123 of 2025
Decided on: 16th May, 2025 ------------------------------------------------------------------------------------- M/s KDN Infrastructure Pvt. Ltd. …..Petitioner
Versus
National Institute of Technology
.....Respondent ------------------------------------------------------------------------------------- Coram Ms. Justice Jyotsna Rewal Dua Whether approved for reporting?1 For the Petitioner: Mr. Suneet Goel, Senior Advocate with Mr. Vivek Negi, Advocate.
For the Respondent: Mr. Kush Sharma, Advocate. ------------------------------------------------------------------------------------ Jyotsna Rewal Dua, Judge
The petitioner is the claimant before the learned Arbitrator. This petition moved under Section 29-A of the Arbitration & Conciliation Act, 1996 (in short ‘the Act’), seeks extension of time for completion of arbitral proceedings by six months w.e.f. 09.01.2025.
2.
Learned Senior Counsel for the petitioner submits that the arbitral proceedings are at the final stages. However, the period allowed for passing the final award has elapsed on 09.01.2025. Hence, prayer has been
1Whether reporters of print and electronic media may be allowed to see the order? Yes.
2 made in this petition moved under Section 29-A of the Act for further extension of the mandate of Arbitral Tribunal.
3.
Taking note of the submissions made by learned counsel on both sides as also keeping in view the fact that the matter is at the stage of arguments, the period for completion of arbitral proceedings including the passing of final award is extended by six months w.e.f. 09.01.2025.
The petition stands disposed of in the above terms, so also the pending miscellaneous application(s), if any.
Jyotsna Rewal Dua May 16, 2025
Judge Mukesh