SIDDIQUE BUILDERS, LKO. THRU. PARTNER SHUAIB AHMAD SIDDUQUI AND ANOTHER v. UNION OF INDIA THRU. SECY. MINISTRY OF RAILWAYS, NEW DELHI AND 3 OTHERS
A227/411/2023 · 2025-04-16
Pankaj Bhatia
body2025
DailyLaw.ai
[ 2025 DAILYLAW 120019 (ALL) · dailylaw.ai ]
DailyLaw.ai
[ 2025 DAILYLAW 120019 (ALL) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
Neutral Citation No. - 2025:AHC-LKO:21431 Court No. - 6 Case :- MATTERS UNDER ARTICLE 227 No. - 411 of 2023 Petitioner :- Siddique Builders, Lko. Thru. Partner Shuaib Ahmad Sidduqui And Another Respondent :- Union Of India Thru. Secy. Ministry Of Railways, New Delhi And 3 Others Counsel for Petitioner :- Rakesh Kumar Tripathi Counsel for Respondent :- A.S.G.I.,Mahendra Kumar Misra Hon'ble Pankaj Bhatia,J.
1. Present petition has been filed for the following relief:
"1. Direct the opposite parties to ensure conclusion of arbitration proceedings arising out of contract agreement No. DRM/LJN/16/2016 dated 24.2.2016 finalised by DRM/Engg. LJN. NE Railways/ Lucknow with M/S Siddique Builders /Lucknow for work "At Lucknow Jn. Station Provision of covering of Balance portion of uncovered area between existing P.F. Shelter to Boundary wall, seating arrangement Railway and covering of remaining portion between concourse end to platform shelter" expeditiously in the ends of justice."
2. Considering the relief as prayed for, present petition is
disposed off with direction to conclude the arbitration proceedings strictly in accordance with law expeditiously preferably within a period of four months.
Order Date :- 16.4.2025 nishant Digitally signed by :- NISHANT MOHAN High Court of Judicature at Allahabad, Lucknow Bench