Extracted from the PDF above. The PDF is authoritative.
2025:HHC:10284 IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA CWP No.5981 of 2025 Date of Decision: 10.04.2025 _____________________________________________________________________ M/s Tesna Tech Private Ltd. ……...Petitioner Versus Union of India & Ors.
…....Respondents Coram Hon’ble Mr. Justice Sandeep Sharma, Judge. Whether approved for reporting? For the Petitioner: Mr. Manik Sethi & Mr. Tawarsu, Advocates. For the Respondents: Mr. Balram Sharma, DSGI, with Mr. Rajeev Sharma, Advocate, for respondents No. 1 to 3- Union of India. Mr. Pushpinder Jaswal, Additional Advocate General, Mr. Sumeet Raj Sharma, Deputy Advocate General with Mr. Rajat Chauhan, Law Officer, for respondent No. 4-State. ___________________________________________________________________________ Sandeep Sharma, J. (Oral) Notice. Mr. Balram Sharma, DSGI and Mr. Pushpinder Jaswal, learned Additional Advocate General, accept notice on behalf of respondents No. 1 to No. 3 and respondent No. 4, respectively.
2.
Learned Counsel for the petitioner submits that the issue raised by the petitioner is squarely covered by the judgment passed by this Court in CWP No. 10600 of 2024, titled as Atul Sharma Versus Union of India & others alongwith connected matters, decided on 06.01.2025 and it would be in the interest of justice, in case, this Writ Petition is disposed of in light of the findings returned by this Court in Para-21 thereof, by ordering that the same be construed to have been passed in the present Writ Petition.
2
3. As it could not be disputed by learned Counsel for the respondents that the matter is squarely covered by the judgment being relied upon by learned counsel for the petitioner, this petition is
disposed of, as prayed for, with the observation that the findings returned in CWP No. 10600 of 2024 (supra), shall be construed to have been passed in the present Writ Petition also. Para-21 thereof is being quoted herein below:-
"21. Consequently, in view of the detailed discussion made herein as well as law taken into consideration, this Court finds merit in the present petitions and accordingly same are allowed with a direction to respondent Nos. 1 and 2 to place the matter before the Empowered Committee chaired by Secretary, DIPP, constitute in terms of Clause 6.1 of the Scheme, for registration expeditiously, preferably within a period of four weeks, without being influenced by letters dated 9.11.2023 and 30.07.2024. Needless to say, petitioners shall be granted incentives, as prayed for, in terms of the Scheme, if they are found eligible. Pending applications, if any, also stand disposed of. Interim order, if any, is vacated."
4. Pending miscellaneous application(s), if any also stand
disposed of accordingly. April 10, 2025 (Sandeep Sharma), (sunil)
Judge