Annai Infra Developers Ltd., v. Bharat Heavy Electricals Limited(BHEL)

A/109/2025 · 2025-01-08

P B Balaji

Transfer Petitionbody2025

Judgment text

Extracted from the PDF above. The PDF is authoritative.

A NO. 109 of 2025 IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 08-01-2025 CORAM THE HONOURABLE MR JUSTICE P.B. BALAJI A NO. 109 of 2025 Annai Infra Developers Ltd., Represented by its authorized signatory Mr.T.Rajendran Door No.2/9,A.N.Towers, Dr Sathyamoorthy Hospital Opposite Road, 2/5, Perundurai Road, Erode-638 011 Applicant(s) Vs Bharat Heavy Electricals Limited(BHEL) (A Govt of India Undertaking) Represented by its Additional General Manager, Power sector,Southern Region, Tek Towers,No 11,OLd Mahabalipuram road, Okkiyam Thoraipakkan,Chennai-600035. Respondent(s) For Applicant(s): No appearance For Respondent(s): Ms.Mithreyi Kasthurirangan ORDER This application has been filed to extend the mandate of the Arbitral Tribunal for a further period of eight months. 2.Heard Ms.Mithreyi Kasthurirangan, learned counsel for the respondent. 1/2 https://www.mhc.tn.gov.in/judis A NO. 109 of 2025 3.I have gone through the affidavit filed in support of the application and I am satisfied with the reasons stated therein. The learned counsel for the respondent also fairly submits that the application can be entertained. 4.Considering the same, the application is allowed and the mandate of the arbitrator is extended by eight months. 08-01-2025 ata To 1. Bharat Heavy Electricals Limited(BHEL) (A Govt of India Undertaking) Represented by its Additional General Manager, Power sector,Southern Region, Tek Towers,No 11,OLd Mahabalipuram road, Okkiyam Thoraipakkan,Chennai-600035. 2/2 https://www.mhc.tn.gov.in/judis