Extracted from the PDF above. The PDF is authoritative.
W.P.(MD)No.1221 of 2025 BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 20.01.2025
CORAM:
THE HONOURABLE MRS.JUSTICE L.VICTORIA GOWRI W.P.(MD)No.1221 of 2025 P. Periyasamy Poosari ... Petitioner Vs.
1. The Chairman,, Tamil Nadu Electricity Board, Anna Salai, Chennai-2.
2. The Superintendent Engineer, Tamil Nadu Electricity Board, Mannarpuram, Trichy.
3. The Executive Engineer,, Operation and Maintenance, Tamil Nadu Generation and Distribution Corporation Ltd., (TANGEDCO), Thuraiyur, Trichy District.
4. The Assistant Engineer,, Operation and Maintenance, Tamil Nadu Generation and Distribution Corporation Ltd., (TANGEDCO), Thuraiyur, Trichy District.
5. The Divisional Engineer,, Operation and Maintenance, Tamil Nadu Generation and Distribution Corporation Ltd., (TANGEDCO), Thuraiyur, Trichy District. ... Respondents 1/5 https://www.mhc.tn.gov.in/judis
W.P.(MD)No.1221 of 2025 PRAYER : Writ Petition filed under Article 226 of the Constitution of India for issuance of a Writ of Mandamus, to direct the Respondents to provide new electricity connection to the Petitioner house situated at No.140/10, North Street, Kottapalayam East, Thuraiyur Taluk, Trichirapalli District. For Petitioner : Mr.R.Krishnamurthy For Respondents : Mr.S.Deenadhayalan Standing Counsel
ORDER Mr.S.Deenadhayalan, learned Standing Counsel takes notice for the respondents. By consent of both the parties, this writ petition is taken up for final hearing at the admission stage itself.
2. The prayer in the Writ Petition reads as follows:-
“To issue a Writ of Mandamus, to to direct the Respondents to provide new electricity connection to the Petitioner house situated at No.140/10, North Street, Kottapalayam East, Thuraiyur Taluk, Trichirapalli District.”
3. Heard the learned counsels on either sides and carefully perused the materials available on record. 2/5 https://www.mhc.tn.gov.in/judis
W.P.(MD)No.1221 of 2025
4. Considering the fact that an electricity connection is a basic necessity, the application made by a citizen of India should not be denied by the respondents.
5. Accordingly, the respondents are directed to provide electricity connection to the petitioner, within a period four (4) weeks from the date of receipt of a copy of this order.
6. With the above said direction, this Writ Petition is disposed of. There shall be no order as to the costs. 20.01.2025 NCC : Yes / No
Index : Yes / No jbr 3/5 https://www.mhc.tn.gov.in/judis
W.P.(MD)No.1221 of 2025 TO:-
1. The Chairman,, Tamil Nadu Electricity Board, Anna Salai, Chennai-2.
2. The Superintendent Engineer, Tamil Nadu Electricity Board, Mannarpuram, Trichy.
3. The Executive Engineer,, Operation and Maintenance, Tamil Nadu Generation and Distribution Corporation Ltd., (TANGEDCO), Thuraiyur, Trichy District.
4. The Assistant Engineer,, Operation and Maintenance, Tamil Nadu Generation and Distribution Corporation Ltd., (TANGEDCO), Thuraiyur, Trichy District.
5. The Divisional Engineer,, Operation and Maintenance, Tamil Nadu Generation and Distribution Corporation Ltd., (TANGEDCO), Thuraiyur, Trichy District. 4/5 https://www.mhc.tn.gov.in/judis
W.P.(MD)No.1221 of 2025 L.VICTORIA GOWRI, J. jbr
Order made in W.P.(MD)No.1221 of 2025 Dated 20.01.2025 5/5 https://www.mhc.tn.gov.in/judis