ANKIT SHARMA ALIAS GIRRAJ v. STATE OF U.P. AND 3 OTHERS
WRIC/41324/2024 · 2025-05-13
S Q H Rizvi
body2025
DailyLaw.ai
[ 2025 DAILYLAW 110801 (ALL) · dailylaw.ai ]
DailyLaw.ai
[ 2025 DAILYLAW 110801 (ALL) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
Neutral Citation No. - 2025:AHC:82626 Court No. - 34 Case :- WRIT - C No. - 41324 of 2024 Petitioner :- Ankit Sharma Alias Girraj Respondent :- State Of U.P. And 3 Others Counsel for Petitioner :- Akhand Pratap Singh,Shobhit Yadav Counsel for Respondent :- Avinash Chandra Srivastava,C.S.C. Hon'ble Syed Qamar Hasan Rizvi,J.
1. Heard Sri Shobhit Yadav, learned counsel for the petitioner; Sri Madan Mohan, learned Standing Counsel for the State-respondent nos.1 to 3 and Sri Avinash Chandra Srivastava, learned counsel for the Land Management Committee-respondent no.4. 2. By means of the present writ petition, the petitioner has prayed for a writ in the nature of mandamus directing the respondent authorities not to build Gaushala over the plot bearing Gata No.311 situated at Village Fatehpura, Tehsil Bah, District- Agra. 3. Submission of the learned counsel for the petitioner is that the petitioner is the bhumidhar of the land bearing Gata No.311 area 0.5940 hectare situated at Village Fatehpura, Tehsil- Bah, District- Agra. He further submits that the adjacent plot bearing Gata No.308 is entered as Naveen Parti in the revenue records. The apprehension of the learned counsel for the petitioner is that the authorities may encroach upon the land of the petitioner and build Gaushala over his plot of land. 4. Learned Standing Counsel appearing on behalf of the State- respondents on the basis of the instructions received from the Sub Divisional Officer (respondent no.3) submits that the land of the petitioner has not been encroached upon and the Gaushala is under
construction over the land belonging to the Gram Sabha i.e. plot bearing Gata No.308/1 which is recorded as Naveen Parti in the revenue records. 5. Learned counsel for the petitioner further submits that the petitioner has already filed an application under Section 24 of the U.P. Revenue Code, 2006 on 30.11.2024, which is still pending for disposal and without deciding the said application for demarcation, the respondent authorities are proceeding with the aforesaid construction. 6.
Taking into consideration the aforesaid situation, without adverting on the merits of the case, this Court is of the view to dispose of the writ petition with a direction to the Sub Divisional Magistrate, Tehsil- Bah, District- Agra (respondent no.3) to conclude the proceedings of the application filed by the petitioner on 30.11.2024 under Section 24 of the U.P. Revenue Code, 2006, strictly in accordance with law, within a period of three months as contemplated under Section 24(3) of the U.P. Revenue Code, 2006. 7. With the aforesaid direction, the present writ petition is
disposed of.
Order Date :- 14.5.2025 Abhishek Gupta Digitally signed by :- ABHISHEK GUPTA High Court of Judicature at Allahabad