MOHD HAFIZ v. UT OF J AND K TH COMMISSIONER SECRETARY TO GOVERNMENT RURAL DEVELOPMENT DEPARTMENT, JAMMU AND OTHERS
WP(C)/3578/2025 · 2025-12-29
Moksha Khajuria Kazmi
Writ Petition (Civil)body2025
DailyLaw.ai
[ 2025 DAILYLAW 10040 (JK) · dailylaw.ai ]
DailyLaw.ai
[ 2025 DAILYLAW 10040 (JK) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT JAMMU
WP(C) No. 3578/2025
Mohd. Hafiz
…..Appellant(s)/Petitioner(s)
Through: Mr. Anil Gupta, Advocate. q
vs
UT of J&K & Ors. .…. Respondent(s)
Through: Mr. Raman Sharma, AAG.
CORAM:
HON’BLE MS. JUSTICE MOKSHA KHAJURIA KAZMI, JUDGE
ORDER 29.12.2025
01. In this petition, petitioner herein has challenged the Technical Evaluation Report dated 14.11.2025 issued by respondent no. 3 regarding construction of Road Dabraj to Moh. Banyian Pyt. Dabraj Block Mankote (S. No. 19), pursuant to tender No. e-NIT 162 of REW dated 18.10.2025, by virtue of which the technical bid of the petitioner was rejected as “not admitted”.
02. Learned counsel for the petitioner states that similar documents submitted by the petitioner have already been considered and admitted by the respondents at serial nos. 17 and 18, and the petitioner’s technical evaluation was shown as responsive.
03. Mr. Raman Sharma, learned AAG, has produced a copy of the communication dated 26.12.2025, which is taken on record, stating that the issue raised by the petitioner has been duly addressed by the department, rejection of the technical bid of the petitioner had
18
2 WP(C) NO. 3578/2025
occurred due to a technical error. Consequently, the petitioner stands qualified for the financial bid.
04. In view of the above statement made by Mr. Raman Sharma, learned AAG, Mr. Anil Gupta, learned counsel for the petitioner, seeks withdrawal of the present petition. His statement is taken on record.
05. Accordingly, the present petition is dismissed as withdrawn along with connected application(s).