RAMESH KUMAR v. THE SECRETARY TO MUNICIPAL ADMINISTRATION
WP/35280/2024 · 2026-03-04
Krishnan Ramasamy
Transfer Petitionbody2024
DailyLaw.ai
[ 2024 DAILYLAW 3476 (MAD) · dailylaw.ai ]
DailyLaw.ai
[ 2024 DAILYLAW 3476 (MAD) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
WP No. 35280 of 2024 __________ Page1 of 6 IN THE HIGH COURT OF JUDICATURE AT MADRAS DATED: 04-03-2026 CORAM THE HON'BLE MR JUSTICE KRISHNAN RAMASAMY WP No. 35280 of 2024 and WMP No. 38190 of 2024 Ramesh Kumar ..Petitioner(s) Vs
1. The Secretary to Municipal Administration and Water Supply, Fort St. George, Chennai 600 009.
2. The Municipal Commissioner, Directorate of Municipal Administration, No.75, Urban Administrative Building, Santhome High Road, MRC Nagar, Raja Annamalaipuram, Chennai 600 028.
3. The Commissioner OF Coimbatore Corporation, Kadaiveedhi Raod, Coimbatore 641 001.
4. Assistant Commissioner South Zone, Coimbatore Corporation, Palakadu Road, Kuniyamuthur, Coimbatore 641 008.
5. The Tahsildar, Perur Taluk, Coimbatore. ..Respondent(s) Prayer: This writ petition is filed under Article 226 of the Constitution of India, praying to issue a Writ of Mandamus forbearing the respondents 3 and 4 from acquiring petitioner land situated at Old Survey 72-part, new survey No.72/4 https://www.mhc.tn.gov.in/judis
WP No. 35280 of 2024 __________ Page2 of 6 Sundakamudhur Village, Coimbatore Tauk, Coimbatore District to an extent of 2175 sq.ft of vacant land without following due process of law on the basis of petitioner representation dated 12.09.2024. For Petitioner(s) : Mr.Venkatesh S. For Respondent(s) : Mr.V.Veluchamy, AGP for R1 & R2 Mr.D.R.Arun Kumar, Standing Counsel for R3 & R4 Mr.T.K.Saravanan, AGP for R5
ORDER This writ petition is filed to forbear the respondents 3 and 4 from acquiring petitioner land situated at Old Survey 72-part, new survey No.72/4 Sundakamudhur Village, Coimbatore Tauk, Coimbatore District to an extent of 2175 sq.ft of vacant land without following due process of law on the basis of petitioner representation dated 12.09.2024. 2. The case of the petitioner is that he has purchased a vacant land situated at Old Survey No.72/part, New Survey No.72/4, Perur Sundakamudhur Village, Perur Taluk, Coimbatore, to an extent of 2175 sq.ft., in the year 2017. However, the respondents 3 and 4 had placed a name board as if the said property belongs to the Corporation. Hence, the petitioner has come forward with the present writ petition. https://www.mhc.tn.gov.in/judis
WP No. 35280 of 2024 __________ Page3 of 6
3. Learned counsel for the petitioner would submit that without due process of law, the respondents are trying to evict the petitioner. It is further submitted that, since the third respondent has already collected the property tax from the petitioner for the subject property, the claim that the land belongs to the Corporation is unsustainable. Accordingly, he prays for appropriate orders. 4. Learned Additional Government Pleader appearing for the respondents would fairly submit that the third respondent has wrongly collected the property tax from the petitioner and as per the approved layout plan, the subject property is earmarked as Children's Play Space and yet to be handed over to the Corporation. 5. Heard the learned counsel on either side and perused the materials available on record. 6. In the present case, the petitioner has purchased the aforesaid vacant land in the year 2017 from the private party. According to the respondents, the subject land belongs to Corporation and earmarked for Children's Park. If the said land is meant for a Park, then it is for the public purpose. It is pertinent to note that the third respondent has collected a property tax from the petitioner for the subject land. Having collected the property tax and earmarked the land for https://www.mhc.tn.gov.in/judis
WP No. 35280 of 2024 __________ Page4 of 6 Children’s park, the respondents supposed to have handed over the subject land to the Corporation. However, in the case on hand, the land was not handed over to the Corporation.
Hence, this Court makes it clear that, in the event, the respondents are taking possession of the subject land, are directed to follow the due procedure of law, since the petitioner is in the possession of the land. With the aforesaid observation and direction, this writ petition stands
disposed of. No costs. Consequently, the connected miscellaneous petition is closed. 04-03-2026 Index: Yes/No Speaking/Non-speaking order Neutral Citation: Yes/No VM https://www.mhc.tn.gov.in/judis
WP No. 35280 of 2024 __________ Page5 of 6 To:
1. The Secretary to Municipal Administration and Water Supply, Fort St.George, Chennai 600 009.
2. The Municipal Commissioner, Directorate of Municipal Administration, No 75, Urban Administrative Building, Santhome High Road, MRC Nagar, Raja Annamalaipuram, Chennai 600 028.
3. The Commissioner of Coimbatore Corporation, Kadaiveedhi Raod, Coimbatore 1.
4. Assistant Commissioner South Zone, Coimbatore Corporation, Palakadu Road, Kuniyamuthur, Coimbatore 641 008.
5. The Tahsildar, Perur Taluk, Coimbatore. https://www.mhc.tn.gov.in/judis
WP No. 35280 of 2024 __________ Page6 of 6 KRISHNAN RAMASAMY J. VM WP No. 35280 of 2024 04-03-2026 https://www.mhc.tn.gov.in/judis