HADIBANDHU MAJHI v. ANU GARG, PRINCIPAL SECY., W.R, DEPT.
CONTC/3801/2023 · 2026-07-31
Aditya Kumar Mohapatra
Writ Petition (Civil)body2023
DailyLaw.ai
[ 2023 DAILYLAW 932 (ORI) · dailylaw.ai ]
DailyLaw.ai
[ 2023 DAILYLAW 932 (ORI) · dailylaw.ai ]
Judgment text
Extracted from the PDF above. The PDF is authoritative.
Page 1 of 1.
IN THE HIGH COURT OF ORISSA AT CUTTACK CONTC No.3801 of 2023 CNR No. ODHC010440702023 Hadibandhu Majhi ..... Petitioner
Represented by Adv. - Mr. Sandeep Rath -versus- Anu Garg, Principal Secretary, Govt. of Odisha, Water Resources Department, Rajib Bhawan, Bhubaneswar and another. ..... Opposite Parties/ Contemnors
Represented by Adv. – Mr. C.M. Singh, ASC
CORAM:
MR. JUSTICE ADITYA KUMAR MOHAPATRA
ORDER 31.07.2026
Order No.
04.
1. This matter is taken up through Hybrid Arrangement (Virtual /Physical Mode).
2. Heard learned counsel for the Petitioner as well as the learned counsel for the Opposite Parties-Contemnors. Perused the contempt application as well as the prayer made therein.
3. By filing the present contempt application, the Petitioner has alleged violation of this Court’s order dated 12.12.2022 passed by this Court in W.P.(C) No.32565 of 2022. By virtue of order dated 12.12.2022, this Court, while disposing of the said writ petition, directing the Opposite Parties to consider the grievance of the
Page 2 of 2. Petitioner in the light of the order passed in similar writ petition.
4.
Learned counsel for the Opposite Parties-Contemnors, at this juncture, contended that the order passed by this Court has already been complied with and that the prayer of the Petitioner has been rejected by passing a speaking and reasoned order dated 11.05.2023 at Annexure-Q to the contempt application.
5. Perused the order dated 11.05.2023 passed by the Engineer- in-Chief, Water Resources, Bhubaneswar, at Annexure-Q to the writ petition. It appears that the Opposite Parties, after due
consideration, have rejected the prayer of the Petitioner. The aforesaid rejection of the Petitioner’s prayer was objected to the
learned counsel for the Petitioner on the ground that the Opposite Parties have taken a decision in violation of the order passed by this Court in the connected writ petition and, in any event, the Petitioner is required to challenge the rejection order dated 11.05.2023, at Annexure-Q to the writ petition, to get any effective relief.
6. Accordingly, the contempt application is disposed of by granting liberty to the Petitioner to challenge the order dated 11.05.2023 passed by the Engineer-in-Chief, Water Resources, Bhubaneswar, at Annexure-Q to the writ petition, if so advised, by filing a fresh writ petition.
(Aditya Kumar Mohapatra)
Judge
Debasis