IN THE HIGH COURT OF ORISSA AT CUTTACK
W.P.(C) No.19027 of 2023
Tofan Kumar Jena …. Petitioner Mr. A.K. Nayak, Advocate
-versus-
State of Odisha & others …. Opp. Parties Mr. U.C. Behura, AGA
CORAM:
THE HON’BLE MR. JUSTICE CHITTARANJAN DASH
Order No.
ORDER 15.04.2026
01.
1. Heard learned counsel for the Parties.
2.
Learned counsel for the Petitioner submits for withdrawal of the case with a liberty to submit a fresh application before the Opposite Party No.4 i.e. Sub-Asst. Engineer, Bidanasi Power Station TATA Power supply Co. Ltd, Cuttack for redressal of his grievance. The same is accepted.
3. In the event the Petitioner submits a representation before the Opposite Party No.4 within a period of fifteen (15) days, the same shall be considered within a period of one month thereafter and to communicate the result thereof within a period of one week.
4. In view of the above, the Writ Petition is dismissed as withdrawn.
(Chittaranjan Dash) Judge
Bijay