HIGH COURT OF JAMMU & KASHMIR AND LADAKH AT JAMMU
CFA No. 11/2007 c/w CFA No. 9/2007
U O I .....Applicant(s)/Petitioner(s)
Through :- None
v/s Bishan & Ors. .....Respondent(s)
Through :- None
CORAM: HON’BLE MR. JUSTICE SANJEEV KUMAR, JUDGE
ORDER 06.02.2026
Notice in these matters was issued on 03.08.2021 & 05.07.2021, respectively. More than four years have passed, the appellant has not taken any steps for the service of respondents in any of the appeals. Today, when the case was called, nobody turned up for the appellant. It seems that the appellant has lost interest to pursue these appeals any further and the same are, accordingly dismissed, for non-prosecution.
The awarded amount, if any, deposited before this Court shall be released in favour of the claimants, after due verification and identification.
(Sanjeev Kumar) Judge
JAMMU 06.02.2026 Manan
Sr. No. 07 Manan Mahajan I attest to the accuracy and authenticity of this document Jammu 07.02.2026 15:19