JUDGMENT Arijit Pasayat, J. - Challenge in this appeal is to the judgment of a Division Bench of the Delhi High Court. Decision taken by a group of Ministers in a matter of joint venture partnership as a part of the privatization policy of the Government of India was assailed before the High Court. 2. According to the appellant, the project has to be grounded because of several major defects which would render the projects take off disastrous. The respondents on the other hand contend that minor technical flaws, if any, have been rectified before the ultimate decision was taken and the project has been rightly held to be in a fit condition to take off. 3. The key players in this dispute are M/s Reliance Airports Developers Pvt. Ltd. (in short ‘RAL’), Airports Authority of India (in short ‘AAI’), Government of India (in short ‘GOI’), GMR Infrastructures Ltd. (in short ‘GMR’), GVK Industries Ltd. (in short ‘GVK’). 4. Background facts sans unnecessary details are as follows: As a part of the GOI’s avowed policy of privatization of strategic national assets, the first step appears to be privatization of two airports i.e. Mumbai and Delhi on a joint venture basis. In March, 2003 AAI initiated process to consider modernization of Delhi and Mumbai Airports on the basis of an earlier decision taken on January 12, 2000 by the Union Cabinet relating to re-structuring of airports of AAI through long term leasing route. On 11.9.2003 the GOI approved restructuring of airports of Mumbai and Delhi through joint venture (shortly called ‘JV’) route and constituted Empowered Group of Ministers (in short ‘EGOM’) to decide the detailed modalities including design parameters, bid evaluation criteria etc. based on which JV partners were to be selected. It was required to submit the final proposal for Government’s approval. An Inter Ministerial Group (in short ‘IMG’) was set up to assist EGOM for re-structuring of two airports. The same was set up under the Chairmanship of Additional Secretary-cum-Financial Adviser of Ministry of Civil Aviation. Subsequently, on 15.6.2004, EGOM was re-constituted under the Chairmanship of Minister of Defence. On 12.10.2004 IMG was re-constituted under the Chairmanship of Secretary, Ministry of Civil Aviation. On the basis of recommendations made by IMG, EGOM approved appointment of Global Technical Adviser, Legal Consultant and Financial Consultant (called GTA, LC & FC in short respectively). Subsequently, on 15.6.2004, EGOM was re-constituted under the Chairmanship of Minister of Defence. On 12.10.2004 IMG was re-constituted under the Chairmanship of Secretary, Ministry of Civil Aviation. On the basis of recommendations made by IMG, EGOM approved appointment of Global Technical Adviser, Legal Consultant and Financial Consultant (called GTA, LC & FC in short respectively). They were Airport Planning Ply Ltd., Amarchand, Mangaldas & Suresh A. Shroff & Co. and ABN AMRO Asia Corporate Finance (I) Pvt. Ltd (in short Airplan, AMSC and ABN AMRO respectively). The Consultants prepared the "Invitation To Register An Expression of Interest" (shortly called ‘ITREOI’) and the same was endorsed by IMG. Subsequently, EGOM approved the same. On 17.2.2004, ITREOI was issued for the two airports. Request for proposal was routed by AAI and the bidders were invited to bid on certain basis and pattern. The tendering process involved two tiers; i.e. an Expression Cum Request for Qualification (in short ‘ECRQ’) and a Request for Proposal (in short ‘RFP’). At the RFP stage, evaluation was carried out in four stages. The first two stages involved verification in the nature of mandatory norms. The third stage was technical evaluation stage and the final stage was financial evaluation stage. On 15.2.2005, EGOM finalized and approved key principles of RFP and draft transaction documents. The RFP documents were issued on 1.4.2005. 5. Certain changes to the draft transaction documents were approved by EGOM. Before such approval, RFP documents of the two airports were forwarded to the bidders. On 30.8.2005 final transaction documents were forwarded to the bidders. The deadline for submissions of bids was fixed as 14.9.2005. There were in fact six bidders for Delhi and five bidders for Mumbai. On 19.9.2005, a meeting of IMG was held relating to methodology for evaluation of offers and evaluation criteria in RFP documents. IMG decided that bid evaluation on all parameters shall be carried out by a composite team of GTA, LC and FC. IMG also decided to set up a review committee to review the evaluation carried out by GTA, LC and FC. The same was also described as an "Evaluation Committee" (in short ‘EC’). 6. The technical bids were opened on 22.9.2005. On 10.10.2005 Government Review Committee (in short ‘GRC’) was constituted to undertake an independent review of evaluation report of bids of two airports and re-structuring process prepared by the Evaluation Committee/Advisers. The same was also desc