Section 11

Amendment status not verified — confirm the current text below against the official source.

The scanned source for this Act is imperfect — headings or section boundaries may be off. Verify against the official source.

(1) Subject to the rules as may be made by the State Government in this behalf, every procuring entity shall pre-determine a reasonable time frame for completion of various stages of the process of procurement and indicate the same in the pre-qualification documents, bidder registration documents or bidding documents, as the case may be. (2) The procuring entity shall endeavour to adhere to the time frame indicated under sub-section (1) and in case of failure to do so extend such time frame for reasons to be recorded in writing. Chapter V Tendering