(1) Any eligible consumer who proposes to install a renewable energy system in his premises shall apply in the form in Annexure-A to the local office of the distribution licensee, to issue feasibility certificate to connect the renewable energy system to the distribution system of the licensee along with the application fee as specified in the Schedule to these Regulations: [Provided that the application forms shall be accepted online or through hard copy or through web portal; Provided further that in case the application form submitted is in hard copy form, the same shall be scanned and uploaded on the website within 3 working days of its receipt and acknowledgement with the registration number for that application shall be generated and intimated to the applicant within this period;] (2) The licensee shall acknowledge the receipt of the application form and register the applications immediately and shall process the application in the chronological order of its receipt. [Provided that in case the application form is received online through web portal of the distribution licensee, the acknowledgement with the registration number shall be generated immediately on submission of application; Provided further that the application shall be deemed to be received on the date of generation of acknowledgement with registration number;] (3) The distribution licensee shall maintain a separate Application Register for reference and records (4) On receipt of the application form for the feasibility certificate to connect the renewable energy system to the grid, the distribution licensee shall undertake technical feasibility within 15 days of the date of receipt of the application and intimate the applicant the feasibility or otherwise as the case may be. (5) While intimating the feasibility for connecting the renewable energy system, the distribution licensee shall furnish to the applicant; (i) the details of documents to be submitted by the applicant along with the scheme for installation of renewable energy system to the distribution system; (ii) the technical specifications as well as other particulars of the grid-tied inverter/equipment and manually operated isolating switch to be installed by the applicant; (iii) the technical specifications and other particulars of the Renewableenergy meter and Net meter. [(6) The application tracking mechanism based on the unique registration number shall be provided by the distribution licensee through web-based application or any other mode to monitor the status of processing of the application like receipt of application, site inspection, meter installation and commissioning, etc.] Inserted by K.G.Ex.No.2381 dt.18/07/2022 (w.e.f.01/08/2022). Inserted by K.G.Ex.No.2381 dt.18/07/2022 (w.e.f.01/08/2022). Inserted by K.G.Ex.No.2381 dt.18/07/2022 (w.e.f.01/08/2022).