Adherence to approved plan and project specifications by promoter.--

Amendment status not verified — confirm the current text below against the official source.

(1) The proposed project shall be developed and completed by the promoter in accordance with the plans and structural designs and specifications as approved by the competent authorities. (2) The promoter shall not alter in any manner the compulsory open spaces of the building or shall not alter the aggregate area of the park, recreational ground, play ground, garden etc., in the approved colony, in which allottees agreed to take one or more building units, without the consent of all such allottees except when such alteration is required by the competent authority due to change in law. (3) In case any defect in such building or materials used, occurred not due to the fault of the allottee, is brought to the notice of the promoter within a period of two years of handing over possession of a building unit, by the allottee or the association from the date of handing over possession, it shall be the duty of the promoter to rectify such defects without collecting additional charge, within reasonable time, and in the event of promoter's failure to rectify such defects within such time, the aggrieved allottees or association shall be entitled to receive appropriate compensation in the manner as provided under this Act.

Section 14 – Kerala Real Estate (Regulation and Development) Act, 2015 | DailyLaw.ai