Amendment status not verified — confirm the current text below against the official source.
(1) Where, within the period specified in Section 235I or 235J, as the case may be, the Secretary has neither given nor refused approval of a building site, or permission to execute any work, as the case may be, the Village Panchayat shall be bound on the written request of the applicant, to determine whether such approval or permission should be given or not. (2) Whether the Village Panchayat does not, within one month from the date of receipt of such written request, determine whether such approval or permission should be given or not, such approval or permission shall be deemed to have been given, and the applicant may proceed to execute the work. But shall not be so as to contravene any of the provision of this Act or any rules or bye-laws made thereunder.