(1) If any licensee fails to comply with the time frame stipulated under Regulation 85 he shall be liable to pay penalty as may be determined by the Commission in accordance with sub-section (3) of Section 43 of the Act. (2) The liability of the licensee to pay penalty under this regulation shall be without prejudice to the liability to pay compensation to the affected person as per the regulation notified under sub-section (2) of Section 57 of the Act. (3) The licensee shall not be held responsible for delay, if any, in extending supply if the same is on account of problems relating to right of way or acquisition of land or court order or any delay on account of causes or force majeure conditions, over which the licensee has no reasonable control.