Bare ActsThe Andhra Pradesh Domestic, Irrigation and Industrial Water Grid Pipelines (Acquisition of Right of User in Land) Act, 2018

Section 4

Amendment status not verified — confirm the current text below against the official source.

Hearing of objections,- (1) Any person interested in the land may, within thirty days from the date of the publication of notification under sub-section(1) of Section 3, object to the laying of the pipelines under the land; (2) Every objection under sub-section(1) shall be made to the competent authority in writing and shall set out the grounds thereof and the competent or by a legal practitioner and may, after hearing all such objections and after making such further inquiry, if any, as that authority thinks necessary, by order either allow or disallow the objections; (3) Any order made by the competent authority under sub-section(2) shall be final.

Section 4 – The Andhra Pradesh Domestic, Irrigation and Industrial Water Grid Pipelines (Acquisition of Right of User in Land) Act, 2018 | DailyLaw.ai